/Knowledge/Predictive Maintenance in Practice: How Data-Driven Maintenance Drastically Reduces Unplanned Downtime

Success Story · 9/7/2026

Predictive Maintenance in Practice: How Data-Driven Maintenance Drastically Reduces Unplanned Downtime

Challenge

Interval-based maintenance without condition data: unplanned downtime, costly emergency repairs, long lead times for special components.

Solution

Retrofit during operation: vibration and temperature sensors on the pumps, LoRaWAN® transmission, a central IoT platform with alerts.

Results

  • 70 % fewer unplanned outages
  • 25 % lower maintenance costs
  • 99 % faster response to anomalies
  • 30 % longer service life of critical components

Unplanned downtime is one of the most costly risks in industrial operations. Especially where continuous processes, safety-critical systems, and high delivery commitments converge, outages are more than just a technical problem—they quickly become a strategic risk.

Predictive maintenance has been considered the solution for years. Yet there is often a gap between theory and practice. Many decision-makers ask themselves:
Does it really work during ongoing operations? In existing plants? Under real-world industrial conditions?

A recent case study from CHEMPARK provides reliable answers to these questions—and shows how data-driven maintenance not only improves processes but also changes the way people think about operations.

Schwingungssensoren im Flusswasserwerk werden montiert

Beyond Maintenance by Blind Flight: Why Traditional Maintenance Is Reaching Its Limits

In many industrial facilities, maintenance still follows fixed intervals. Pumps, motors, and compressors are inspected—regardless of whether they show any signs of abnormalities. This approach conveys a sense of security but creates a dangerous situation of flying blind.

Without continuous condition data, early signs of wear remain hidden. Damage is often not detected until anomalies have already reached a critical stage. The consequences are:

  • unplanned downtime
  • expensive emergency repairs
  • long lead times for specialty components

It was precisely against this backdrop that the question was reframed at CHEMPARK:
What if maintenance were based not on assumptions, but on real-time data?

Case Study Overview: Predictive Maintenance at CHEMPARK

The following case study documents a real-world project for condition monitoring of high-performance pumps in a chemical industrial environment. It illustrates not only the technical implementation but, above all, the operational effects of predictive maintenance.

Quick Overview for Decision-Makers

CategorySummary
Industry / EnvironmentChemical Industrial Park (critical infrastructure)
Initial SituationReactive, interval-based maintenance
ObjectiveReduction of unplanned downtime
SolutionIoT-based Predictive Maintenance
ImplementationRetrofit during ongoing operations
TechnologiesSensors (vibration, temperature), LoRaWAN®, IoT platform
Key Results–70% reduction in unplanned outages, –25% reduction in maintenance costs
Time to ValueLive data within a few weeks
TransferabilityHigh (pumps, rotating assets, brownfield)

From Reacting to Taking Action: The Success Story Behind the Numbers

Initial Situation: Reactive Maintenance as a Risk

In the plant section under review, those responsible operated a large number of rotating machines. Despite regular inspections, unplanned outages occurred time and again. The condition of the pumps was known—but only in isolated cases.

Looking back, one person involved summarized the situation as follows:

“We knew failures would happen—but not when. That made planning nearly impossible.”

The Turning Point: Condition Data Instead of Empirical Values

The decisive step was not to further optimize maintenance, but to change the approach. Instead of rigid intervals, condition data was continuously collected. Vibrations and temperatures provided early indications of deviations from normal operation.

The goal here was not maximum data depth, but the ability to act early. Anomalies were to be detected before they escalated into damage.

Implementation at a Glance: Retrofit Instead of New Construction

A key success factor was the decision to pursue a retrofit scenario. Existing pumps were retrofitted with industrial-grade sensors—without disrupting ongoing operations.

Data was transmitted wirelessly via LoRaWAN®. A central IoT platform aggregated the information, visualized trends, and automated notifications when thresholds were exceeded.

The result: Live data was available within a few weeks. Operations did not need to be restructured, but simply reimagined.

What Really Made the Difference—The Results

The solution’s impact was clearly measurable:

  • 70% fewer unplanned downtimes
    Unexpected shutdowns were virtually eliminated.
  • 25% lower maintenance costs
    Maintenance efforts focused on truly relevant assets.
  • 99% faster response time to anomalies
    Minutes instead of days between detection and action.
  • 30% longer service life for critical components
    Early intervention prevented consequential damage.

These figures are not theoretical targets, but were achieved in real-world operations.

Murat Mutlu, IoT portfolio manager at Conneqtive, describes the transformation as follows: “Today, we no longer react to damage, but to signals. That gives us control.”
(Note: Is Murat the source of this quote? Or: “A technical manager…”)

Lessons Learned from Implementation

Several overarching insights can be derived from the case study:

  1. Early detection is more cost-effective than perfection

It’s not about analyzing every detail, but about identifying relevant deviations early on. You don’t save time by collecting more data, but by making better decisions.

  1. Retrofitting is the realistic starting point

Predictive maintenance is not exclusive to new construction. Existing facilities can also be made data-capable with manageable effort.

  1. Platforms accelerate time-to-value

Using an existing IoT platform drastically shortens implementation times and reduces project risks.

  1. Condition-based maintenance changes processes—and mindsets

The greatest impact is not technical, but organizational: maintenance shifts from reacting to planning.

Transferability: A blueprint for other industrial environments

Although the project focuses on high-performance pumps, the underlying approach is widely transferable:

  • rotating assets (pumps, motors, fans, compressors)
  • regulated industries
  • brownfield environments
  • safety-critical infrastructure

What matters is not the specific use case, but the combination of sensor technology, connectivity, and clear decision-making rules.

Context: Why This Case Study Is More Than Just a Single Project

What makes this case study particularly valuable is not just the result, but its context. It shows that predictive maintenance is no longer an experiment, but a robust operational model—when implemented pragmatically.

The real added value arises when such projects are not viewed in isolation but are used as a blueprint for further use cases.

Conclusion

This case study provides solid answers to one of the central questions of industrial digitalization:
Does predictive maintenance really work in everyday operations?

Yes, when technology, processes, and the vision align.